The South UHL Road Improvement Project is a collaborative effort between the City of Glenn Heights and the City of Red Oak to enhance the roadway from Ovilla Road to the intersection of Harmony Way. The City of Red Oak is leading the project, with Glenn Heights contributing $2.4 million as part of an Interlocal Agreement (ILA) established in October 2023.
The City of Red Oak finalized its plans in June 2023 to construct only half of the roadway. At that time, the City of Glenn Heights initiated discussions and proposed a partnership to upgrade the entire section to final conditions. As a result, the design consultant revised the plans to incorporate these enhancements. The updated plans are now nearing completion, pending TxDOT approval for drainage and traffic signal improvements and HILCO’s coordination on existing utility adjustments along the corridor.
Project timeline:
1st Publication: May 14th
2nd Publication: May 21st
Bid Closing/Reading of the Bids: May 28 @ 2pm
Bid Verification/Bid Tab: June 2nd/3rd
RO Council Award: June 9th
GH Council Award: June 17th
Contract Execution: by July 17th
Notice to Proceed: Aug 4th
Preconstruction Meeting: Aug 19th
Utility Relocation: 7-10 business days after Aug 19th
Hilco is in the process or relocating existing electrical power lines underground.
The Contractor for the roadway has mobilized onsite and will begin work the first week of March.
§Dec 2026 – projected completion date
* S UHL RD Construction Plans (Link)
For more details, the primary point of contact is Mr. Jared Binford with the City of Red Oak.